|
Advisory
Committee
Meeting #6
Brooke-Hancock-Jefferson
Bridge Study Advisory Committee
March 15, 2000
Below
are the minutes taken by Lisa Kush for the Bridge Study Committee conducted
on March 15, 2000 at the Brooke County Library Public Library, Wellsburg,
West Virginia. This is a full list of attendees and description of happenings.
On March
15th, at 1:30 p.m., the Bridge Advisory Committee was called
to order by Chairman David Snelting. The meeting proceeded in the following
manner.
- Minutes from
the February 16th meeting were unanimously approved as
submitted. by the committee.
- Caleb Faux, Project
Manager for the Bridge Study and a member of the consultant firm of
Plum, Klausmeier & Gehrum (PKG) introduced a summary memorandum,
which outlined the consultants findings to date regarding issues related
to the question of a need for additional river crossing capacity in
the project study area. The summary outlined 10 conclusions, seven
of which supported the need to move into Phase
2, bridge location.
- Included in the
summary report, was the goals and objectives established by the Coordinating
Committee,
a summary report analyzing the condition of the existing bridges,
results of the Traffic Operations Analysis, and the results of the
Travel Demand Modeling process used to project future traffic. Also
included in the report were preliminary conclusions drawn from data
that had been assembled by the firm.
- PKG suggested
in the Bridge Condition Analysis that considering the age of the Market
Street Bridge and the Ft. Steuben Bridge, both are nearing the end
of their useful life.
- Rehabilitation
to the Market Street Bridge would slow down the rate of deterioration;
however PKG concluded that the bridge would still remain deficient
in both roadway geometric and load-carrying capacity. Rehabilitation
work would not include upgrades to the bridges cables and piers.
Estimated upgrade costs was approximated at nearly $4.5 million.
- Rehabilitation
to the Ft. Steuben Bridge was estimated to range near the $5 million
mark. PKG concluded that the costly repairs to the bridge would
exclude the possibility of widening the roadway and no increase
in traffic congestion. PKG did not factor in future development
of a river port regarding traffic congestion. Furthermore the firm
concluded that with the Veteran’s Memorial Bridge nearby the Ohio
Department of Transportation, who owns the bridge, may have a difficult
time securing funding for the bridge.
- Included in the
preliminary study, Modjeski and Masters, Inc., developed cost estimates
for a new Ohio River Crossing within the study area. Estimates were
gathered on three variations, including short, medium and long river
crossings. Those estimates ranged from a short structure at $40 million
to $77 million for a long structure. The estimates were based on construction
costs in today’s market and did not include ramping ingress and egress.
PKG said estimated costs for total bridges construction would likely
exceed the $100 million mark.
- Results of the
traffic analysis concluded that the projected growth in river crossing
demand would in all likelihood not increase significantly if all three
bridges remained open. If one or both bridges in the future is deemed
inoperable, an increase in demand on the Veteran’s Memorial Bridge
would not be excessive. However, the study does indicates that double
river crossings would decrease in the event the two older bridges
are closed, which would reduce the number of river crossings. On the
flip side, the consultants said if the Veteran’s Memorial Bridge would
be closed, as it is at least one a year for routine inspections, both
of the older bridges sustain a heavy increase in traffic volume.
- Lastly, the summary
concluded that in the event that only one river crossing would exist
within the metropolitan area, a hazard would be created in relation
to emergency situations and that is unacceptable.
The meeting
adjourned at 2:50 p.m. A public information meeting followed at the Jefferson
Community College. Mr. Faux announced that the next meeting would be held
on April 26th at 1:30 p.m., at the Jefferson Community College
4000 Sunset Blvd. Room 2000. A public information sharing meeting will
held in May, date and tine to be announced. Phase 1 of the Bridge Study
will be concluded in May.
Following
the advisory committee meeting, the consultants held the second of three
public information sharing meeting. The meeting was held at the Jefferson
Community College in Steubenville, Ohio. Approximately 30 residents from
the BHJ region attended the meeting. The consultants reiterated their
summary report to the residents. A final report will be submitted in May.
| Persons
Present: |
|
| Will
Allison |
Hancock
County Economic Development Authority |
| Vicki
Baird |
Alliance
2000 |
| Don
Bailey |
West
Virginia Department of Transportation |
| Frank
Bovina |
Village
of Mingo Junction |
| John
Brown |
Brooke-Hancock-Jefferson
Planning Commission |
| Caleb
Faux |
Pflum,
Klausmeier & Gehrum Consultants |
| Adrian
Freund |
Pflum,
Klausmeier & Gehrum Consultants |
| Greg
Gurney |
Ohio
Department of Development |
| W.
Duane Heck |
Brooke
County Commission |
| Russ
Irvin |
City
of Wellsburg |
| Perry
Keller |
Pflum,
Klausmeier & Gehrum Consultants |
| Lisa
Kush |
Brooke-Hancock-Jefferson
Metropolitan Planning Commission |
| Bob
Laukert |
Village
of Wintersville |
| Marilyn
McCord |
Brooke
County Republican Party, Executive Committee |
| Karen
Monaco |
Ohio
Department of Development |
| Mike
Paprocki |
Brooke-Hancock-Jefferson
Planning Commission |
| Shawn
Price |
Brooke-Hancock-Jefferson
Planning Commission |
| Norm
Schwertfeger |
Brooke
County Commission |
| David
Snelting |
City
of Steubenville |
| Mary
Kay Wallace |
Brooke
County Public Library Director |
|